THE
RED RIVER SAGA RECON REPORT - JULY 20, 2009 |
||||||||
The
construction project will replace an existing steel bridge with timber
decking that was built in 1954. Over the years, this bridge has become
deficient and unsafe for large road maintenance equipment and fish stocking vehicles. The existing bridge will be replaced with a single span steel girder structure with concrete decking. The new bridge will provide safe access for the public & support road maintenance activities, as well as future stream & fish habitat restoration projects. Recreational visitors in the Indian Creek area are encouraged to use caution during the construction project and to avoid the immediate vicinity where heavy equipment will be operating. For more information, contact the Cumberland Ranger District office at 606-784-6428 or the Gladie Learning Center at (606) 663-8100 [CLICK HERE] to Read the USFS Official Announcement [CLICK HERE] to Download the FS Road 9 Closure Flyer [CLICK HERE] & [CLICK HERE] for Forum Threads |
||||||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
![]() |
||||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
|||||||
![]() |
![]() |
![]() |
![]() |
|||||
Click on Thumbnails at Right for Larger Views This is the appearance of the Indian Creek Bridge on Monday, July 20th, 2009 approximately 8:00am ET We encourage anyone who journeys there with the sole purpose of status checking to do so only after the day's work is complete. Please do not become an issue with the Bridge Construction Crew over the remaining days. Photos you would like to submit of the work? Send them to us [CLICK HERE] |
||||||||
![]() |
![]() |
![]() |
![]() |
|||||
THE
RED RIVER SAGA RECON REPORT - JUNE 22nd, 2009 |
||||||||
Road
closure at Indian Creek - Contact: Kimberly Morgan WINCHESTER, Ky., June 15, 2009 – Beginning Monday, June 22, the Indian Creek Road in Menifee County, Forest Service Road #9 in the Red River Gorge, will be closed for construction. The closure is expected to span over a period of at least 90 days as contractors remove and reconstruct a bridge over the East Fork of Indian Creek. During this time, the road will be closed to vehicle traffic in the interest of public safety. “We realize this road leads to a popular area of the gorge where many visitors enjoy fishing, hiking and rock climbing,” said Dave Manner, District Ranger of the Cumberland Ranger District, “but the bridge repairs are necessary to improve travel in this area.” The construction project will replace an existing steel bridge with timber decking that was built in 1954. Over the years, this bridge has become deficient and unsafe for large road maintenance equipment and fish stocking vehicles. The existing bridge will be replaced with a single span steel girder structure with concrete decking. The new bridge will provide safe access for the public & support road maintenance activities, as well as future stream & fish habitat restoration projects. Recreational visitors in the Indian Creek area are encouraged to use caution during the construction project and to avoid the immediate vicinity where heavy equipment will be operating. For more information, contact the Cumberland Ranger District office at 606-784-6428 or the Gladie Learning Center at (606) 663-8100 [CLICK HERE] to Read the USFS Official Announcement [CLICK HERE] to Download the FS Road 9 Closure Flyer [CLICK HERE] & [CLICK HERE] for Forum Threads |
||||||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
![]() |
![]() |
|||||
![]() |
![]() |
![]() |
![]() |
|||||
Click
on Thumbnails at Right for Larger Views This is the appearance of the Indian Creek Bridge on Friday, June 19th, 2009 approximately 1:00pm ET It is hoped that during the downtimes of the upcoming construction we may acquire some photos of the work in progress. We assume that foot travel is still permitted into the area. We encourage anyone who journeys there with the sole purpose of status checking to do so only after the day's work is complete. Please do not become an issue with the Bridge Construction Crew over the next 90 days. Photos you would like to submit of the work? Send them to us [CLICK HERE] |
||||||||
![]() |
![]() |
![]() |
![]() |
|||||
RRS
RECON PAGE 4 - - FS ROAD 9 RETAINING WALL CONSTRUCTION >>>>>>>>> |
||||||||